KICC framework agreement for comprehensive maintenance of ICT equipment, network, data centre and AV equipment (Tender KICC/21/2026-2028)

Official title: FRAMEWORK AGREEMENT FOR PROVISION OF COMPREHESIVE SERVICE AND MAINTEINANCE OF ICT EQUIPMENT, NETWORK DEVICES, DATA CENTER INFRASTRUCTURE AND AUDIO VISUAL (AV) EQUIPMENT

Closing
Thu 19 Nov 2026, 10:30 am EAT
Tender number
TENDER NO. KICC/21/2026-2028
Procuring entity
The Kenyatta International Convention Centre
التصنيف
Non Consultancy Services · Framework Agreements

Official documents take precedence. NairobiCity is an independent information service, not the procuring entity or a government body. This summary was prepared from the official documents with AI assistance; every requirement was matched to the document wording, but it can still contain mistakes. Before you apply, read the official tender documents and any addenda.

What is being bought

Framework agreement for comprehensive service and maintenance of ICT equipment, network devices, data centre infrastructure and audio visual (AV) equipment for Kenyatta International Convention Centre, Nairobi. Quantities and exact sites are not stated in the reviewed pages; the price schedules refer to ministry and government institution sites.

What could disqualify you

  • Failure to comply with mandatory requirements in the preliminary examination leads to disqualification. D1 p.32
  • Perfect binding or hard cover binding is required; box files with loose pages or loose-leaf pages are not acceptable. D1 p.33
  • Bidders not completing the cost breakdown schedule will automatically be disqualified. D1 p.36
  • Bidders not providing mandatory unit rates for spares and consumables will be disqualified; rates above prevailing market rates may lead to disqualification. D1 p.43
  • Tenders received after the deadline are declared late, rejected and returned unopened. Standard rule D1 p.20
  • A tender not accompanied by a substantially responsive Tender Security shall be rejected; tender-securing declaration is required here. Standard rule D1 p.19

Key facts

Closing
Thu 19 Nov 2026, 10:30 am
Tender submission deadline. Current date and time after all addenda: no addenda reviewed. D1 p.29
Bid / tender security
A Tender Security is not required; a Tender-Securing Declaration is required, in the form in Section IV. The amount of a Tender Security is not applicable. D1 p.29
Tender fee
Not stated in the documents we reviewed Not stated D1
Site visit
إلزامي
Tenderer is required to visit the service sites before tendering to ascertain existing conditions of ICT equipment, network and infrastructure. The general ITT wording encourages site visits; the price schedule text says the tenderer shall visit. D1 p.35
Pre-bid meeting
Not stated in the documents we reviewed Not stated D1 p.15
Reserved for
No reservation to SME, women, youth or persons with disability; the invitation is open to all bidders. D1 p.28
Contract value
Performance Security of Kshs.50,000 in form of Unconditional Demand Bank Guarantee. Contract value not stated; monthly charges are priced per equipment item in the schedules. D1 p.30
Tender opening
Tender opening at KICC 4th Floor, Harambee Avenue, on the same day as closing. D1 p.29
Tender validity
Tender validity period is 121 days from the submission deadline. D1 p.29

Who can apply

  • The invitation is open to all bidders; reservation to special groups is not applied (margin of preference not allowed). D1 p.28

Application checklist

Tick items off as you prepare. Your ticks stay on this device only.

Required from every bidder

  • D1 p.32
  • D1 p.32
  • D1 p.32
  • D1 p.32
  • D1 p.32
  • D1 p.32
  • D1 p.32
  • D1 p.32
  • D1 p.33
  • D1 p.33
  • D1 p.33
  • D1 p.33
  • D1 p.33
  • D1 p.33
  • D1 p.33
  • D1 p.33
  • D1 p.36
  • D1 p.43

Required only in some situations

  • D1 p.14
  • Standard rule D1 p.17

How and where to submit

  • Physical written submission only; electronic submission not permitted. Deliver in a single sealed envelope bearing tender name and reference number, addressed to the Procuring Entity, with ORIGINAL and COPIES envelopes; inner envelopes show Procuring Entity and tenderer names and reference number. D1 p.28
  • Address: Attention Chief Executive Officer, Postal 30746-00100 Nairobi; physical address Kenyatta International Convention Centre (KICC), 4th Floor, Harambee Avenue. D1 p.28
  • Original plus one copy required (TDS: number of copies is One in addition to the original). D1 p.29
  • Documents must be sequentially paginated in Arabic numerals on every page including attachments, perfect or hard cover binding. D1 p.33
  • Tenderer must sign the Form of Tender and all pages where entries are made; authorisation by Power of Attorney or written authorization. D1 p.29

Lots and categories

  • The tender is not split into lots in the reviewed pages; tenderers may tender for any one or more Service Lines/Lots, evaluated lot-wise. D1 p.23

What the addenda changed

  • No addenda were provided for review. Not stated P

Points to confirm with the procuring entity

The documents do not agree with each other on these points. Ask the procuring entity for a written clarification before you submit.

  • Tender security type: TDS says a Tender Security shall not be required and a Tender-Securing Declaration shall be required, but the preliminary examination checklist requires a Tender Securing declaration form, and ITT 21.1 text is ambiguous; confirm the form to submit with the procuring entity. (D1 p.29 (TDS ITT 21.1); D1 p.33 (Section III criterion 17))
  • Site visit: ITT 7.1 says the site visit is encouraged; the price schedule text says the tenderer shall visit the sites before tendering. Confirm whether a site visit is mandatory. (D1 p.14 (ITT 7.1); D1 p.111 (Schedule of Payments))
  • Submission method: Portal lists written physical submission, while ITT 24 mentions electronic submission only where the TDS specifies it; TDS says electronic submission is not permitted, which is consistent. (P (portal record); D1 p.23 (ITT 24))

Not covered in the documents we reviewed

  • Quantities, locations and list of ICT equipment, network devices and AV items to be maintained (Section V Procuring Entity's Requirements, BOQ)
  • Full Section III evaluation scoring (technical and financial criteria, minimum scores)
  • Section IV tendering forms and Form of Tender content, including Form of Tender Securing Declaration
  • Contract duration details and Intended Completion Date (Framework Agreement period beyond the 36-month pricing reference)
  • Pre-tender meeting or site visit date and time, if any (TDS ITT 8.1)
  • Financial requirements such as minimum turnover amounts and years (Section III qualification criteria)
  • Any addenda after the original document
  • Preferred procurement complaint and standstill details beyond the TDS summary

Terms explained

Framework Agreement
A standing agreement with selected suppliers under which orders are called off as needed during the period, rather than a single fixed contract.
Tender Securing Declaration
A signed declaration, in the prescribed form, that the bidder will not withdraw during validity and will sign the contract and provide performance security; no bank guarantee is needed.
Performance Security
Security a successful bidder provides after award to guarantee performance, here Kshs.50,000 as an unconditional demand bank guarantee.
TDS
Tender Data Sheet: the tender-specific section that overrides the general Instructions to Tenderers.
AGPO
Affirmative action preference for youth, women and persons with disability; not applied to this tender per the reviewed pages.
Responsive
A tender that meets all mandatory requirements of the tender documents; non-responsive tenders are rejected.
Power of Attorney
Written authority allowing a named person to sign and bind the company to the tender.
MR
Not used in the reviewed pages.